Golden Gate Village Redevelopment Monthly Report May 2024

May 16, 2024

You can also download a copy of the Golden Gate Village Redevelopment Monthly Report below. If you have any trouble accessing or reviewing the document, please contact us here

Download Golden Gate Village Redevelopment Monthly Report May PDF Document Here

SIGNED AGREEMENT WITH BURBANK


  • An agreement (“ENRA”) giving MHA the Exclusive Right to Negotiate with Burbank Housing was approved by MHA’s Board and signed on April 24th.
  • The ENRA is the next step in the predevelopment process of GGV. It serves as a roadmap for MHA and for Burbank, outlining a year-long process as the parties progress towards a Master Development Agreement.
  • This process includes due diligence, preliminary design, cost analysis, resident input, and community engagement.
  • Burbank will lead and manage the due diligence and conceptual design phase, while MHA provides funding to cover predevelopment costs.



ALL GGV RESIDENTS GET TO STAY AT GGV


  • HUD Notices PIH-2019-09 and PIH 2019-23 protect residents during the conversion of a community from Public Housing to Project-based: no resident of GGV can be involuntarily displaced or forced to move due to the redevelopment and conversion of GGV.
  • If a resident is incorrectly housed before conversion from public housing or becomes incorrectly housed at conversion, they may remain in their unit until an appropriate-sized unit becomes available.
  • MHA and the GGV Resident Council have agreed that incorrectly housed residents with the longest stay at GGV would move last.
  • MHA can grant exceptions to occupancy standards based on health, age, sex, disability, medical or employment needs, right to return and other circumstances as outlined in HUD 24 CFR 982.402(b)7.